Project: mhlRV14A   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Mark Larsen   -  
Project:   Vans - RV-14A
Total Hours:1661.5
Total Flight Time:
Start/Last Date:Sep 21, 2020 - No Finish Date
Engine:Lycoming YIO-390-EXP119 (YENPL-RT2E11172)
 
Friendly URL: https://eaabuilderslog.org?s=mhlRV14A

Home or Last Project Picture

Nov 08, 2020     Skin Drilling and Deburring - (4.5 hours) Category: 6 Vertical Stab
The vertical stabilizer skin has 206 holes that need to be drilled to final size plus 4 more that need to be match-drilled into the forward flange areas of the tip and nose ribs. The holes in the skin are already final size, which made the final-size drilling of the substructure go quickly. When all the drilling was complete, everything gets disassembled to enable deburring of the holes and edges and prep for primer. I deburred the holes in the skin and decided to call it a day.

I will continue deburring holes in the ribs and spars tomorrow, but the edges will have to wait a few days until I get a couple more deburring accessories. It's also time to make some decisions about priming – like where I'm going to do it!
 